The Challenge
This property required rapid ADA compliance corrections under an extremely tight timeline. The objective was to remove exterior accessibility barriers identified through a CASp inspection and report while minimizing disruption to normal operations.
The schedule was highly compressed. The CASp inspection and report were completed in less than one week, and the corrective construction work was executed in just three days — covering demolition, installation of new ADA concrete work, asphalt tie-ins, and compliant striping and signage.
Maintaining long-term slope performance was critical. Key accessible areas had to remain below the 2% cross-slope threshold, particularly in locations where asphalt alone can shift over time and create future compliance risk.
The Solution
Protrk® implemented an integrated fast-track design-build approach that coordinated evaluation, planning, and construction execution within a single controlled scope. This streamlined process allowed the team to move from inspection findings to corrective construction rapidly while maintaining strict compliance standards.
Key Actions Taken:
- Coordinated CASp report findings and translated recommendations into a build-ready construction scope
- Sequenced demolition and removal of non-compliant asphalt and concrete conditions to maintain the accelerated schedule
- Installed new ADA concrete parking areas, access aisles, and accessible routes engineered to maintain compliant slopes longer than asphalt surfaces
- Completed asphalt integration and tie-ins to restore drivability immediately after concrete installation
- Installed compliant striping, pavement markings, and ADA signage to clearly designate accessible stalls and routes
- Performed compliance documentation and closeout support aligned with voluntary accessibility upgrades
All work was executed in tightly coordinated phases to ensure the construction window remained limited and the property could return to full operation as quickly as possible.
The Result
The project was completed in just three days, delivering measurable exterior accessibility improvements while minimizing operational disruption.
The property received updated ADA parking stalls, access aisles, accessible routes, and compliant signage. Path-of-travel conditions were improved and documented closeout support was provided, strengthening the property's overall compliance posture.
Project Outcomes:
- Completed a 3-day fast-track ADA construction upgrade
- Delivered improved ADA parking and access aisle compliance
- Improved exterior accessible path-of-travel conditions
- Installed compliant ADA striping, markings, and signage
- Minimized operational disruption during construction
- Provided documented compliance support for voluntary accessibility upgrades